![Falsework / Structural system Falsework / Structural system](https://www.pdfsearch.io/img/12e770f133f7e5670e58c659ae4ca51d.jpg) Date: 2014-08-22 18:38:39Falsework Structural system | | Month of Aug 2014 B) Construction of the Pier 3 pier table will be completed this month. Contractor will remove the forms and stress transverse loop tendons that were cast into the concrete. The tendons serve the same pu